Works are well underway in stabilising the cliff face with Geomarine being in the process of installing over 1,000 soil-nails and anchors.
Additional ground investigation was required by the clients design team in order to finalise detailing at the toe of the slope. The unique location and logistical issues with the site led to Geomarine chartering a landing craft to deliver a 21 tonne excavator to dig trial pits which were subsequently logged by both Geomarine and others which lead to the decision making of how to deal with the stabilisation.